Major Milestones
Here's the text from our quad chart amended somewhat in the light of
information we obtained at the workshop.
- Release PLEXUS environment for time-critical planning, 9/95.
- Distribute benchmarks for TCIMS, USTRANSCOM, and AMC/ACP, 6/96.
- Test model-acquisition methods on sanitized AMC/ACP data 9/96.
- Release prototype solution for AMC/ACP problem in PLEXUS 6/97.
The only changes involve the hedge (AMC/ACP versus AMC) on the
primary target for our demonstration domain. At this point I plan to
be opportunistic moving toward whichever group is more forthcoming
with data and feedback. The TIE we are proposing with Rockwell and
U of Washington is aimed at ACP and from the San Diego meeting it
would appear that ACP is the more likely domain.