Group
 Logic
 Graphics
 GUI
 File I/O & Sound


Sunday Monday Tuesday Wednesday Thursday Friday Saturday
March 2 3 4 5 6 7
Top Level Design
8
March 9 10 11 12
Interface Proposals
Component Testing Plans
13 14
Final Interface
Directory/CVS Setup
15
March 16 17
Detailed Design Proposals
Begin Taking Pictures
18 19
Determine Design
20 21
Final Interface Handin
Detailed Design Complete
22
March 23 24 25 26 27 28 29
Mar/Apr 30 31
Begin Coding
File format specified
Begin research on school
1 2 3 4
Detailed Design Handin
Loading function complete; Sound files ready
Rough Graphics Engine
Primitive GUI
5
April 6 7
Testing Assignment Handin
Begin basic features & Map
8 9 10 11
Individual components compile with minimal functionality
Saving function complete; Playback complete
Main buildings modeled
GUI buttons complete
12
April 13
Individual Component Testing
14
Initial Integration
15
Begin testing and debugging with driver
16 17 18
Individual Components Completed
Begin Integration and Debugging
19
April 20 21 22 23
Coding & Full System Integration Complete
Testing & Debugging
24 25 26
Apr/May 27 28
Public Demo
29 30 1 2
Public Demo in Lubrano
3
May 4 5 6 7 8 9
System Submission